Maryland State Highway Administration (Maryland) posted this RFI on Nov 17, 2026. Responses are due Dec 18, 2026. Category: Construction - Heavy & Civil. Solicitation number BPM059773.
This bid was found on the agency's procurement portal. The portal's own text is not republished here; the summary below was written by ProposalWorkspace's AI from the bid documents. The full posting is on the portal - subscribe to get the link.
Summary fields on this page were extracted by AI from the bid documents. Always verify dates, amounts and requirements against the official solicitation.
The Maryland Department of Transportation State Highway Administration (SHA) is issuing this Presolicitation Information Memorandum (PIM) for the proposed American Legion Bridge and I-270 Multimodal Corridor project (the Project). The Project covers approximately 4 miles of I-495 from the northern limit of the Virginia I-495 Express Lanes near the George Washington Memorial Parkway to the I-270 west spur, and approximately 2 miles along the west spur to north of Westlake Terrace. The Project represents a phase of improvements evaluated in the I-495 & I-270 Managed Lanes Study (MLS), which received a federal Record of Decision (ROD) in August 2022.
This PIM provides a high-level commercial overview to inform industry participants of the opportunity under consideration prior to any formal solicitation. Information here is for planning and feedback purposes only.
The Project’s technical scope includes adding two new High Occupancy Toll (HOT) managed lanes in each direction on I-495 from south of the George Washington Memorial Parkway in Virginia to the I-270 west spur. On the I-270 west spur, the Project proposes to convert one existing High Occupancy Vehicle (HOV) lane in each direction to a HOT managed lane and add one new HOT managed lane in each direction from I-495 to north of Westlake Terrace.
Core Commercial Frameworks
Key Physical and Environmental Constraints
- Thomas Branch Stream Relocation: The alignment requires the relocation of the Thomas Branch stream parallel to I-495 and the I-270 west spur. Preliminary designs call for converting a significant portion of this open channel into a structural subterranean box culvert beneath the widened interstate roadway.
SHA is using this PIM to gather industry input before deciding whether to advance any solicitation. No decision has been made to deliver the Project as a P3 or to proceed with any solicitation.
Confidential, one-on-one market-sounding meetings with Qualified Respondents who satisfy at least one of the following criteria are planned to be held:
Qualified Respondents must complete and submit a *One-on-One Meeting Request Form* by **December 18, 2026** to schedule a meeting in January 2027. The form is available online at https://americanlegionbridge270.com/presolicitation-information-memorandum/. All responses will be handled in accordance with the Maryland Public Information Act.
Subscribe to get this document.