Data Colocation Center RFI

Active 99SWC-S4091 RFIInformation TechnologyGovernor's Technology Office
The full text, documents and contacts of this bid come with a ProposalWorkspace plan.Get started

At a glance

Governor's Technology Office (Nevada) posted this RFI on Nov 20, 2026. Responses are due Dec 24, 2026. Category: Information Technology. Questions are due 2026-12-04 16:00. Solicitation number 99SWC-S4091.

Solicitation details

General information

Solicitation number
99SWC-S4091
Notice type
RFI
Place of performance
Nevada
Questions due
2026-12-04 16:00

Agency and category

Agency
Governor's Technology Office
Category
001Information Technology
Source listing
Link with a plan

Description

From the agency listing

The State of Nevada is seeking comprehensive technical and budgetary information from qualified commercial data center operators to evaluate state-of-the-art enterprise colocation facilities, redundant high-density power delivery, carrier-neutral meet-me rooms, dedicated optical transport services, outside-plant fiber connectivity for state broadband initiatives, and direct cloud adjacency across Northern and Southern Nevada.

Summary

AI-read from the bid documents

Summary fields on this page were extracted by AI from the bid documents. Always verify dates, amounts and requirements against the official solicitation.

What the bid is for

The State of Nevada is seeking comprehensive technical and budgetary information from qualified commercial data center operators to evaluate state-of-the-art enterprise colocation facilities, redundant high-density power delivery, carrier-neutral meet-me rooms, dedicated optical transport services, outside-plant fiber connectivity for state broadband initiatives, and direct cloud adjacency across Northern and Southern Nevada.

This solicitation is a request for information (RFI) only. It is not a solicitation for bids or proposals. No contract award will result from this RFI.

Scope

Geographic Facility Requirements

Respondents must operate commercial colocation facilities in both regions of Nevada:

  • Northern Nevada Facility: Situated in Northern Nevada (e.g., Reno, Sparks, Tahoe-Reno Industrial Center [TRIC], or Carson City).
  • Southern Nevada Facility: Situated in the greater Las Vegas metropolitan area.

Both facilities must be located outside 500-year floodplains and major commercial flight hazard paths, and meet stringent regional seismic structural standards.

Data Center Certification Requirements

Both the Northern Nevada Facility and Southern Nevada Facility shall be concurrently maintainable and fault tolerant facilities certified as Tier IV by Uptime Institute, or possess an equivalent internationally recognized certification demonstrating Tier IV fault-tolerant design and operational characteristics.

Physical Footprint & Cabinet Capacity

  • Northern Baseline Footprint: Eight (8) standard 42U/48U enclosed server cabinets.
  • Southern Baseline Footprint: Eleven (11) standard 42U/48U enclosed server cabinets.
  • Total Baseline: Nineteen (19) cabinets across both facilities.

Electrical Power Architecture, Metered Billing & Renewable Energy

Each facility must deliver 100% concurrently maintainable A/B redundant electrical power backed by diverse UPS systems and on-site emergency diesel generators with minimum 48-hour continuous run-time fuel reserves.

Metered Power Model: Respondents must detail their capability to support metered power billing based on actual kilowatt-hour (kWh) consumption plus a certified PUE multiplier, alongside traditional flat-rate committed circuit billing.

Carrier-Neutral Meet-Me Rooms & OSIT Middle-Mile Fiber Interconnect

Facilities must feature true carrier-neutral Meet-Me Rooms (MMR) with diverse physical Points of Entry (POEs) and redundant internal riser pathways.

Mandatory Carrier Presence: Physical on-net presence is required for the State's incumbent telecommunications providers, including AT&T, Lumen/CenturyLink, Cox Communications, Zayo, and CC Communications.

Inter-Facility Optical Transport & Blended Internet Transit

Dedicated Optical Wavelengths: Ability to procure or cross-connect to point-to-point dedicated 10 Gbps and 100 Gbps optical wavelengths connecting Northern Nevada to Southern Nevada, and connecting data centers to the State Capitol Complex (575 E. 3rd St, Carson City) and the University of Nevada, Reno (UNR).

Cloud Adjacency & Contract Elasticity

Direct Cloud On-Ramps: On-net presence or low-latency private direct interconnects to Microsoft Azure ExpressRoute, AWS Direct Connect, and Google Cloud Interconnect.

Additional information

Submission

Information should be submitted as a quote through nevadaepro.com. Technical information and cost information should not be included in the same attachment. Additional attachments may be included.

Responses containing confidential trade secret should be submitted as two separate attachments in nevadaepro.com: a complete marked version flagged as confidential, and a redacted public version.

Responding to this RFI is voluntary. A response will not give a respondent any advantage in, and declining to respond will not disqualify a vendor from, any subsequent solicitation.

Timeline

All questions shall be submitted using the bid Q&A feature in nevadaepro.com by the deadline below. All times stated are Pacific Time (PT). These dates represent a tentative schedule of events. The State reserves the right to modify these dates at any time.

  • Deadline for questions: No later than 4:00 pm on 12/04/2026
  • Answers posted: On or about 12/11/2026
  • Submission deadline: No later than 2:00 pm on 12/24/2026