The Niagara Frontier Transportation Authority (“NFTA”) will receive bids on a general contract for the MTC – Courtyard Waterproofing Improvements & Accessible Connection. Project Number 15TB2301.
The work shall include, but not be limited to:
Replacement of an existing 2nd floor exterior courtyard roofing system, including sand bed and pavers with new waterproofing membrane, insulation, and adjustable pedestal paver system. The project also includes modifications to plumbing, HVAC, and electrical systems, installation of new egress doors and providing an accessible connection to the courtyard. See Specification Section 011100 for a general summary of work.
Bids will be accepted either in offline (paper) or online (electronic) versions. Offline bids should be submitted in an opaque sealed envelope to the Engineering Branch on the 7th floor of the MTC. The lower left-hand corner should be marked as follows: BID NO. E-639. Online bids should be submitted in accordance with the process outlined on the NFTA’s Engineering Branch website.
Bid security must accompany each bid and must be in an amount not less than **ten percent** of the total bid price if the base bid exceeds **$50,000.00**. Bid security may be submitted prior to bid opening either electronically utilizing Surety2000 at www.surety2000.com, or delivered to the NFTA in an opaque sealed envelope.
The Contractor shall perform not less than 30% of the Work with its own forces.
The time of completion for the project is 120 calendar days after receipt of the Notice to Proceed.
Liquidated damages will be assessed against the Contractor for its failure to complete the project within the time specified.
A walk-through of the project site will be conducted directly following the Pre-Bid conference.