Opportunity for DBE - R156-R02 Upgrade of Main Sewage Pump and Power Distribution Systems

Active 2140634 RFQConstruction - Heavy & CivilNew York City Department of Environmental Protection
The full text, documents and contacts of this bid come with a ProposalWorkspace plan.Get started

At a glance

New York City Department of Environmental Protection (New York) posted this RFQ on Nov 9, 2026. Responses are due Dec 18, 2026. Category: Construction - Heavy & Civil. Solicitation number 2140634.

Solicitation details

General information

Solicitation number
2140634
Notice type
RFQ
Place of performance
New York

Agency and category

Agency
New York City Department of Environmental Protection
Category
006Construction - Heavy & Civil
Source listing
Link with a plan

About this listing

ProposalWorkspace summary

This bid was found on the agency's procurement portal. The portal's own text is not republished here; the summary below was written by ProposalWorkspace's AI from the bid documents. The full posting is on the portal - subscribe to get the link.

Summary

AI-read from the bid documents

Summary fields on this page were extracted by AI from the bid documents. Always verify dates, amounts and requirements against the official solicitation.

What the bid is for

Jett Industries, Inc. (Jett - Contractor) is assembling a bid for the R156-R02 MSP Power Dist Upgrades with NYCDEP (Owner) and extends this request for Quotes (RFQ) to all firms (Bidders) to provide labor, materials, and/or equipment for the Project as described in these bid packages.

The Rockaway Wastewater Resource Recovery Facility (WRRF) is owned and operated by DEP. This Project's objective is to improve the continued operational reliability of the Rockaway WRRF in compliance with updated code requirements and operational optimization by upgrading and replacing its main sewage pump (MSP) and power distribution systems, both of which have reached the end of their useful life. The Project shall also provide odor control to specific areas to reduce potential complaints.

Scope

The major elements of work are as follows:

  • Replacement and upgrade of the MSP System:
  • Five West Drywell MSPs in service.
  • The 48-inch force main header for the existing MSPs, that discharges into the WRRF’s four primary sedimentation tanks (PST).
  • Six submersible pumps in service.
  • The 42-inch force main header for the submersible pumps that discharges into the PSTs.
  • Permanent demolition of two out-of-service East Drywell MSPs.
  • Upgrades to the drywell MSP and ancillary support systems, including leveling metering.
  • Flow metering equipment, remote monitoring and control for the new MSP system.
  • Power sub-metering of the MSPs.
  • Related ancillary systems, including motor control centers (MCC), lighting panels and systems, and heating, ventilation, and air-conditioning (HVAC).
  • Replacement and upgrade of the Power Distribution System:
  • Standby Generator System.
  • Main Incoming Feeders.
  • Main Power Distribution Systems, including replacement of the 5 kilovolt (kV) and 13.2 kV substation and switchgear (SWGR) systems.
  • 12 MCCs.
  • HVAC and Lightning Systems.
  • Temporary Interim Systems.
  • Related ancillary systems.
  • Interconnection and excess distribution costs coordination with the Long Island Power Energy and Gas (LIPSEG), the local power distribution utility, to accommodate the Project.

The Project also includes necessary work to meet the NYC and DEP’s resiliency guidelines and requirements, as well as applicable NYC Local Laws for Sustainability per GPR Section 01 36 63 - Sustainability Requirements. The Design-Builder (DB) is responsible for identifying any applicable updates and including them in the scope of work. [...] The Work will occur in an active WRRF requiring continuous uninterrupted operation per GPR Section 01 72 12 – Maintenance of Operation and Construction Staging and requirements in this Volume.

Additional information

**All quotes should be submitted through the Building Connected platform.** Contact the scope lead if there are any questions or issues with submissions.

Project documents and Scope details will be posted to the Files tab of Building Connected.

Jett will upload to the FILES tab on Building Connected all addenda as received by the Owner. A notification through Building Connected will be sent to Bidders. Bidders are required to acknowledge receipt of addenda in writing on the *Bid Proposal* form or their quote.

Any Bidder, no later than the date posted on the Project Information Page, may submit questions for interpretation or clarification of, or addenda to, this Bid. All requests must be submitted in writing and sent by email or as a message through Building Connected.

This project has a 20% DBE participation goal.