Engineering Services for CUP Switchgear Controls Upgrade

Active RFSQ #26-2936 RFSQArchitecture & EngineeringDenton County
The full text, documents and contacts of this bid come with a ProposalWorkspace plan.Get started

At a glance

Denton County (Texas) posted this RFSQ on Nov 13, 2026. Responses are due Dec 3, 2026. Category: Architecture & Engineering. Questions are due 2026-11-25 14:00. Solicitation number RFSQ #26-2936.

Solicitation details

General information

Solicitation number
RFSQ #26-2936
Notice type
RFSQ
Place of performance
Texas
Questions due
2026-11-25 14:00

Agency and category

Agency
Denton County
Category
007Architecture & Engineering
Source listing
Link with a plan

About this listing

ProposalWorkspace summary

This bid was found on the agency's procurement portal. The portal's own text is not republished here; the summary below was written by ProposalWorkspace's AI from the bid documents. The full posting is on the portal - subscribe to get the link.

Summary

AI-read from the bid documents

Summary fields on this page were extracted by AI from the bid documents. Always verify dates, amounts and requirements against the official solicitation.

What the bid is for

The intent of this solicitation is to obtain the professional services of a qualified engineering firm to provide engineering design and construction administration services for the upgrade of the main switchgear controls at the Denton County Administrative Complex Central Utility Plant (CUP), located at 701 Kimberly, Denton, TX 76208. The project includes replacement of outdated computer control components built into the electrical switchgear.

Denton County is requesting Qualification Statements from firms who can adequately demonstrate they have the resources, experience and qualifications to provide the County with quality engineering services.

Scope

The awarded firm shall be responsible for all phases of design and construction administration required to successfully complete the project from initial programming through close-out. The Scope of Services will include coordination with the appropriate related entities of Denton County.

Project Scope of Work

The project consists of replacing the electrical computer control components within the main switchgear at the CUP. The awarded firm shall provide engineering design and construction documents for the following:

1. Switchgear Controls Upgrade: Evaluate the existing computer control components within the main switchgear and design their replacement with current, supported components. Include associated hardware, software, programming, wiring, and other modifications necessary to complete the upgrade.
2. Generator and Utility Power: Evaluate the existing control sequence for transfer between utility and generator power. Design the upgraded controls to operate with the existing generators, switchgear, and associated electrical equipment.
3. Manufacturer Coordination: Coordinate with the applicable equipment manufacturers and service providers to confirm compatibility, installation requirements, and ongoing support for the proposed replacement components.
4. Installation and Operational Coordination: Develop installation and transition requirements in coordination with Denton County to minimize interruptions to operations at the Elections/Technology Services Building and the CUP. Identify required outages and any temporary measures needed during installation.
5. Testing and Commissioning: Provide requirements for testing and commissioning the upgraded controls, including verification of generator operation and transfer between utility and generator power.
6. Code Compliance and Coordination: Evaluate the proposed improvements for compliance with applicable electrical codes, safety standards, and other governing requirements. Coordinate the controls upgrade with existing electrical systems and County operational requirements.

If additional work is identified as necessary during the design process, the awarded firm shall notify Denton County and obtain approval before proceeding with services outside the approved scope.

The awarded firm shall field-verify existing conditions as necessary and coordinate all electrical, controls, and other required engineering design elements to provide a complete, coordinated set of construction documents.

Additional information

Submission

Respondent may submit qualification statements electronically by uploading documents required in Section V. Qualification Statements, at Denton County partner's website, Bonfire (https://dentoncounty.bonfirehub.com). If you choose to submit in hard copy, submit one original paper copy of your submittal to the office of the Director of Purchasing PRIOR to the stated deadline. Sealed Qualification Statements will be received PRIOR to and publicly opened at 2:00 P.M. on THURSDAY, DECEMBER 3, 2026. Late statements will not be accepted. Respondents shall not submit pricing in this package.

Evaluation

The Request for Qualifications will be evaluated using a point system (100) on the following categories.

  • Tab 1 – Firm Qualifications (40)
  • Tab 2 – Technical Qualifications (60)

Oral presentations may be conducted with the most qualified firms. Competitive Range scoring will total 200 points.

Contract Term

The term of the contract shall be from the execution of the Contract until completion or termination of the project, at the discretion of Denton County Commissioners Court.

Site Visit

A site tour will immediately follow the pre-submission conference.