Grays Harbor Transportation Authority In-ground Hoist Replacements Project

Active GHT-2026ITB01 ITBConstruction - BuildingGrays Harbor Transportation Authority
The full text, documents and contacts of this bid come with a ProposalWorkspace plan.Get started

At a glance

Grays Harbor Transportation Authority (Washington) posted this ITB on Nov 19, 2026. Responses are due Jan 5, 2027. Category: Construction - Building. Questions are due 2026-11-25 15:00. Solicitation number GHT-2026ITB01.

Solicitation details

General information

Solicitation number
GHT-2026ITB01
Notice type
ITB
Place of performance
Washington
Questions due
2026-11-25 15:00

Agency and category

Agency
Grays Harbor Transportation Authority
Category
005Construction - Building
Source listing
Link with a plan

About this listing

ProposalWorkspace summary

This bid was found on the agency's procurement portal. The portal's own text is not republished here; the summary below was written by ProposalWorkspace's AI from the bid documents. The full posting is on the portal - subscribe to get the link.

Summary

AI-read from the bid documents

Summary fields on this page were extracted by AI from the bid documents. Always verify dates, amounts and requirements against the official solicitation.

What the bid is for

Grays Harbor Transportation Authority (“GHTA”), the public transportation provider in Grays Harbor County, Washington, is requesting bids for the In-Ground Hoist Replacements Project.

Replace two (2) existing in-ground hoists with two (2) new code-compliant, modular in-ground, axle engaging bus lifts and controls in Bay 2 and 3 at the Grays Harbor Transit Hoquiam Maintenance and Operations Facility located at 705 30th Street, Hoquiam, WA 98550. [...] The new hoists will be furnished by GHTA. The Contractor is to ensure the delivery of the hoist equipment is coordinated with the hoist installer.

Scope

Work includes demolition and decommissioning of existing hoists, modifications to existing structural foundations, electrical improvements required to support the new lift systems, coordination and management of new hoist installation (to be installed by manufacturer approved installer), associated site restoration, removal of existing hose reels and installation of new hose reels in Bays 2 and 3, removal of the existing waste oil tank in Bay 2, and relocation of the existing anti-freeze tank.

Existing equipment and utilities that conflict with the new installation shall be removed, relocated, or modified as required. Construction shall be phased such that one hoist remains operational during replacement of the other. There shall be minimum disruption of on-going maintenance and administrative activities outside of Bay 2 and 3.

Bids shall include all labor, equipment, transportation, and materials to complete the specified work. Bids shall also include mobilization and demobilization to and from the Project site.

Project Milestones

The Contractor’s schedule shall identify and provide anticipated scheduled dates for achieving the following project milestones.

  • On-site Construction Start
  • Phase 1 Completion – Maintenance Bay 100 (N) / Bay 2
  • Phase 2 Completion – Maintenance Bay 101 (S) / Bay 3
  • Substantial Completion
  • Final Completion – including inspections, commissioning and Owner sign-off
  • Demobilization Complete

The Administration – Maintenance Facility Building is an operational facility. Access for vehicle maintenance operations shall be maintained during construction based on the phasing details provided in the project drawings.

Additional information

**Submission method:** Electronic bids must be submitted and successfully uploaded to the Agency’s secure procurement portal located at https://mrscrosters.bonfirehub.com/opportunities/260132 no later than Tuesday, January 5, 2027, at 11:00 AM Pacific Time. The system will automatically lock at the deadline, and any part of a Bid Form or bid modification not fully uploaded prior to this time will not be considered.

All bid components must be submitted in a secure, text-searchable, non-editable PDF format. Substitute or alternate bid forms will not be considered. Bidders must segment their digital submittals into separate files:

1. [Bidder Name]_File 1_Bid Form and Pricing.pdf
2. [Bidder Name]_File 2_5 (Five) Percent Bid Bond.pdf
3. [Bidder Name]_File 3_Statutory Certifications.pdf

Bids will be publicly opened and read aloud via a virtual Zoom meeting at 1:30 PM, following the portal closure.

The Engineer's Estimate is **$540,000 to $610,000**.

All work performed for this project is subject to Washington State prevailing wage rates.

An optional pre-bid meeting and site visit will be held on-site at Grays Harbor Transit, 705 30th Street, Hoquiam WA 98550.

Earliest Anticipated Notice-to-Proceed: 1/20/2027.

Documents

5 files

Subscribe to get these 5 documents.

  • Bid Proposal Forms.pdf
    Download
  • GHTA In-Ground Hoist Replacement Project Technical Specifications.pdf
    Download
  • GHTA In-Ground Hoist Replacements Project Manual.pdf
    Download
  • ITB Drawing Set Plans.pdf
    Download
  • Sample Contract.pdf
    Download