Ben Franklin Transit (Washington) posted this IFB on Nov 23, 2026. Responses are due Dec 22, 2026. Category: Construction - Heavy & Civil. Questions are due 2026-12-11 10:00. Solicitation number OpenGov-d5b57207.
This bid was found on the agency's procurement portal. The portal's own text is not republished here; the summary below was written by ProposalWorkspace's AI from the bid documents. The full posting is on the portal - subscribe to get the link.
Summary fields on this page were extracted by AI from the bid documents. Always verify dates, amounts and requirements against the official solicitation.
Ben Franklin Transit, (hereinafter referred to as BFT), a municipal corporation of the State of Washington, located at 1000 Columbia Park Trail, Richland, WA 99352, is soliciting bids from qualified firms to provide the following services listed below.
BFT is soliciting bids from qualified contractors to provide irrigation system improvements and decommissioning of two existing irrigation wells at its Maintenance, Operations, and Administration (MOA) facility in Richland, Washington.
The project includes installation of a new irrigation water service and meter, connection to the existing irrigation system, permanent decommissioning of two existing wells, associated utility and electrical work, surveying and easement documentation, and site restoration in accordance with the project plans and specifications.
This project will transition the existing irrigation system from well water to the City of Richland's municipal water supply.
The Contractor shall provide a complete, functioning City-water-fed irrigation service and permanently decommission two existing irrigation wells. Work includes utility connections, a new water meter assembly, irrigation tie-in, electrical isolation, well closure, surveying and easement documentation, turf restoration, testing, coordination and all incidental work shown on the contract drawings or reasonably necessary for completion. The Contractor shall coordinate specialty subcontractors, including a Washington-licensed well driller, appropriately licensed electrical personnel and a professional land surveyor.
City Water Service and Irrigation Meter
Connection to Existing Irrigation System
Decommission Two Existing Irrigation Wells
A Washington State licensed well driller shall permanently decommission both wells in accordance with RCW 18.104, WAC 173-160 (including WAC 173-160-381), Ecology requirements and applicable local requirements. [...] After well closure, fill the existing concrete well vault with crushed rock to the bottom of the lid as shown in C002 Keynote 5.
Electrical Isolation and Equipment Removal
- At the well vault, remove pump power conductors and conduit back to the edge of the vault and cap as shown by C002 Keynote 8.
Survey and City Water Easement
- Provide a Washington professional land surveyor-prepared, signed/stamped legal description and exhibit for the proposed 10-foot-wide water line easement centered on the existing water line, suitable for City review and recording.
Landscape, Grading and Site Restoration
- Remove the entire lawn within the area identified by C002 Keynote 9, not merely the trench footprint. Evenly regrade topsoil, protect the existing irrigation system and replace the full designated lawn area with new sod.
Closeout
Final payment will not be released until BFT accepts the complete Closeout Package.
BFT prefers **electronic submission** of bids via the e-Procurement Portal: https://secure.procurenow.com/portal/bft. Mail-in responses will be accepted and must be accompanied by an electronic copy on a USB key included in the response envelope. If mailing a hard copy response, please send 2 response(s).
All bids shall be accompanied by a suitable **bid security in the amount of 5% of the bid amount**. Suitable security shall mean cash, cashier's check, or bond from a firm licensed to do business in the State of Washington.
Contractor offer will be valid for ninety (90) calendar from due date of bids.
Contract will be awarded to the most responsive and responsible based who provided the lowest overall bid cost.
Provide one comprehensive lump-sum price for the complete project. Separately identify the cost of well decommissioning and irrigation improvements for BFT evaluation, without excluding either from the total.
BFT reserves the right to issue a Notice to Proceed at any time up to twenty (20) calendar days following Award of the Contract.
Contractor's one-year warranty letter (starting at Final Acceptance) and all manufacturer warranties are required in the closeout binder.
A Public Bid Opening will be held on Microsoft Teams at the submission due date and time.