California Department of Fish and Wildlife (California) posted this IFB on Nov 19, 2026. Responses are due Dec 17, 2026. Category: Construction - Building. Solicitation number 0000040984.
Provide all labor, tools, equipment, materials, incidentals, permits and taxes necessary to replace seventy (70) retrofit windows, install one Americans with Disabilities Act (ADA) compliant ramp, and other miscellaneous work on six (6) state-owned residences located at San Joaquin Hatchery.
Location of Services: San Joaquin Hatchery 17372 Brooktrout Friant, Ca 93626
**Mandatory** Jobwalk ¿ Wednesday, December 2, 2026 @ 10:00 AM
License Required: A or B
Estimated Cost: **$ 150,000.00**
Participation in Disabled Veteran Business Enterprise Program (DVBE): The minimum DVBE participation percentage goal is 3%. Failure to fulfill the DVBE requirement will render your bid non-responsive. DVBE Incentive: For evaluation purposes only, an incentive will be given to bidders who exceed the 3% DVBE participation requirements. Refer to the Instructions to Bidders.
Small Business Preference and Small Business Subcontractor participation: A five percent (5%) Small Business Preference will be granted to properly certified small businesses (a copy of your certification must be submitted with the bid proposal).
As of March 1, 2015, Senate Bill 854 requires that ¿No Contractor or subcontractor may be listed on a bid proposal for a public works project unless registered with the Department of Industrial Relations for projects greater than $25,000.00¿. Failure to register with DIR or list sub-contractors not registered will render your bid non-responsive.
Summary fields on this page were extracted by AI from the bid documents. Always verify dates, amounts and requirements against the official solicitation.
The Contractor shall furnish all labor, tools, equipment, materials, incidentals, permits, taxes and incidentals necessary to replace seventy (70) retrofit windows, install one Americans with Disabilities Act (ADA) compliant ramp, and other miscellaneous work on six state-owned residences located at San Joaquin Hatchery.
Location of Services: San Joaquin Hatchery, 12373 Brooktrout Drive, Friant, CA 93626, Fresno County
Estimated Cost: **$150,000.00**
Items of Work
All items of work on the contract form are to be complete in place.
Time of Completion
Construction shall be completed within **SIXTY (60) WORKING DAYS** following the official "Notice of Start Date" from CDFW to the Contractor to commence construction.
License Required
Other Requirements
The Contractor shall furnish the Contract Manager a proposed work schedule THREE (3) DAYS PRIOR TO BEGINNING WORK.
The Contractor shall submit shop drawing(s), manufacturer's data for all equipment and materials proposed for use on this job, complete with descriptions, information, and performance data to the Engineer for approval in Portable Document Format (PDF).
Upon completion of each maintenance/service activity under this contract, the Contractor must remove all remaining excess materials, waste, rubbish, debris, temporary facilities, and other equipment from the site.
All work is to be complete in place, in strict accordance with these specifications, and as shown on the California Department of Fish and Wildlife Drawing No: H08-2024-003 Dated: 05/01/2025 Sheet(s): Two (2)
Submission
The bid must be transmitted in a **sealed envelope** in accordance with IFB instructions. This *Bid/Bidder Certification Sheet* must be signed and returned along with all the "required attachments" as an entire package with original signatures.
Evaluation
The award, if there is an award, will be made on the basis of the Total Bid #1. In the case of a tie bid, the determination of a successful bidder will be made by a coin toss in the presence of all interested bidders.
The minimum DVBE participation percentage goal is **3%**. A five percent (5%) Small Business Preference will be granted to properly certified small businesses.
Bonds and Insurance
The above policies must each be endorsed to include "The State of California, its officers, agents and employees as additional insured but only with respect to work performed under the Contract".
Contract Term
Upon DGS approval through December 30, 2027
Site Visit
The Contractor shall visit and determine the actual condition of the site prior to submitting the bid.