RFQ/P Progressive Design-Build Project Reference No. DB-2026-01 - Kane Spring Project

Active 0000040201 RFPConstruction - Heavy & CivilCalifornia Department of Water Resources
The full text, documents and contacts of this bid come with a ProposalWorkspace plan.Get started

At a glance

California Department of Water Resources (California) posted this RFP on Aug 27, 2026. Responses are due Dec 4, 2026. Category: Construction - Heavy & Civil. Solicitation number 0000040201.

Solicitation details

General information

Solicitation number
0000040201
Notice type
RFP
Place of performance
California

Agency and category

Agency
California Department of Water Resources
Category
006Construction - Heavy & Civil
Source listing
Link with a plan

Description

From the agency listing

The Department of Water Resources (Department) is issuing this Request for Qualifications and Proposals (RFQ/P) to obtain Statements of Qualifications and Proposals (SOQ/Ps) from Submitters qualified to serve as the Design-Builder for the Progressive Design-Build (PDB) Kane Spring Project (Project) located along the southwest shore of the Salton Sea near the City of Brawley. The Project is being procured using a one-step, Best Value selection method.

Kane Spring is a multi-benefit Project that will include water-based and vegetation-based dust control measures, additional shoreline bird habitat, improved water use efficiency within the Project Site, and wetlands enhancement. To accomplish this, the project will include the design and construction of ponds, ditches, berms, vegetation enhancement, and wetlands enhancement.

The Department has established a website (Cosmos) for the distribution of RFQ/P documents and Addenda and, as applicable, other background documents for the Project. Access to Cosmos is obtained by emailing DWR-CDP@water.ca.gov and providing the following information:

Each Company that is interested gaining access to Cosmos and submitting a Statement of Qualifications must provide the following information:

1. Company Name.
2. The full name, email address and phone number of the Contact Person for this project.
3. Physical address for overnight delivery (PO Box Address not allowed).

For any questions regarding this DWR construction project, please send an e-mail to DWR-CDP@water.ca.gov.

Summary

AI-read from the bid documents

Summary fields on this page were extracted by AI from the bid documents. Always verify dates, amounts and requirements against the official solicitation.

What the bid is for

The Department of Water Resources (Department) is issuing this Request for Qualifications and Proposals (RFQ/P) to obtain Statements of Qualifications and Proposals (SOQ/Ps) from Submitters qualified to serve as the Design-Builder for the Progressive Design-Build (PDB) Kane Spring Project (Project) located along the southwest shore of the Salton Sea near the City of Brawley.

The Project is being procured using a one-step, Best Value selection method as described in Section 4.

Scope

This Project serves to use the following potential water sources (1) existing agricultural drains, (2) groundwater wells, (3) the existing Species Conservation Habitat (SCH) Project, (4) the West Interception Ditch – to maximize the acreages of the following land use objectives (in order of priority):

  • Create and enhance vegetated wetland for California Black Rail and Yuma Ridgway’s Rail
  • Create pupfish habitat
  • Improve existing wetlands by removing salt cedar and tamarisk (Tamarix) and discouraging future salt cedar and tamarisk (Tamarix) growth
  • Create vegetated areas to prevent lakebed from being emissive

The Design-Builder’s work on the Project would include two phases, the Design and Preconstruction Phase (Phase 1) and the Construction Phase (Phase 2). The two phases of PDB work are outlined below:

  • Phase 1: Design and Preconstruction. If the Department awards a PDB Contract to the Design-Builder, it will collaboratively provide design, site investigation, permitting, cost estimating, scheduling and sequencing, and construction planning services to the Department. [...] Phase 1 will include 100% complete design and may overlap with the start of Phase 2.
  • Phase 2: Construction. Phase 2 Work will only be completed if the Department and the Design-Builder successfully reach agreement on GMP Proposal(s) and execute Phase 2 Amendment(s) to the PDB Contract. During this phase, the Design-Builder will construct the Project, conduct commissioning and startup services, successfully complete Performance Tests to achieve Acceptance, and provide support services as defined in the PDB Contract.

Additional information

**Statement of Qualifications and Proposal due:** December 4, 2026.

The Department is requesting SOQ/Ps describing the Submitter’s: 1) team organization and capacity to conduct the Work; 2) project management experience and capabilities; 3) collaboration and effective use of PDB and/or CMCG/CMAR; 4) team qualifications and experience; 5) Project approach, and 6) PDB Price Proposal.

Failure to submit an SOQ/P in accordance with the requirements of this RFQ/P may be cause for disqualification of the Submitter.

The Department intends to award a Progressive Design-Build Contract (PDB Contract) to the selected Submitter which will include a scope of work for Phase 1 Design and Preconstruction Services and may be amended for Phase 2 Work.

The maximum allowable attendance per Submitter at the **mandatory** site visit is 4 people from each company that comprises the Submitter team.

All one-on-one meetings will be virtual. Meeting requests will only be granted to Submitter teams, not individual companies.

Documents

4 files

Subscribe to get these 4 documents.

  • DB-2026-1_RFQ_P_Kane_Spring_Addendum_1.pdf
    Download
  • Kane_Spring_Project_Info_Letter_No_1.pdf
    Download
  • Kane_Spring_Project_Info_Letter_No_2.pdf
    Download
  • Kane_Spring_Project_Info_Letter_No_3.pdf
    Download

Similar open bids

In California

More from California Department of Water Resources

Open bids