CHANGE ORDER NOTICE: Black Hawk SHS Museum Window Dormer Repairs & Replacements

Active 27-422DNR-REALT-B-54809 RFQConstruction - BuildingIllinois Department of Natural Resources
The full text, documents and contacts of this bid come with a ProposalWorkspace plan.Get started

At a glance

Illinois Department of Natural Resources (Illinois) posted this RFQ on Nov 9, 2026. Responses are due Nov 24, 2026. Category: Construction - Building. Solicitation number 27-422DNR-REALT-B-54809.

Solicitation details

General information

Solicitation number
27-422DNR-REALT-B-54809
Notice type
RFQ
Place of performance
Illinois

Agency and category

Agency
Illinois Department of Natural Resources
Category
005Construction - Building
Source listing
Link with a plan

Description

From the agency listing

Change Order to increase cost due to additional labor and materials required to install gutters and downspouts.

Summary

AI-read from the bid documents

Summary fields on this page were extracted by AI from the bid documents. Always verify dates, amounts and requirements against the official solicitation.

What the bid is for

Change Order to increase cost due to additional labor and materials required to install gutters and downspouts.

New 24ga Prefinished Steel Dark Bronze Gutters and Downspouts: **ADD: $35,182.00**

Remove Rot From Top Side of Door Lintel and Epoxy Repair: **ADD: $2,000.00**

Total Add: **$37,182.00**. Contract add days: **14 days**.

Scope

New 24ga Prefinished Steel Dark Bronze Gutters and Downspouts

  • Cut back existing roof edge to flush up with new 2x8 painted sapele skirt board.
  • Furnish and install 80' of 7" 24ga prefinished steel gutter on 16ga s.s. hangers 24" o.c.
  • Furnish and install 30' of 5" square corrugated prefinished steel downspouts.
  • Furnish and install 6" of prefinished steel edging and sill flashings.
  • Furnish and install 5" under gutter prefinished steel closure flashing.

Remove Rot From Top Side of Door Lintel and Epoxy Repair

  • Carve rot from top side of door lintel beam.
  • Treat area with Abatron Liquid Wood Epoxy
  • Fill area with Abatron WoodEpox.

Additional information

We reserve the right to request an increase if markets fluctuate from current standings.

Documents

2 files

Subscribe to get these 2 documents.

  • CO Quote - Black Hawk Gutters.pdf
    Download
  • Change Order Notice V.25.1 8.28.24~43.pdf
    Download