2027 Concrete Replacement Projects

Active ITB 27-20051-AE ITBConstruction - Heavy & CivilCity of Lubbock
The full text, documents and contacts of this bid come with a ProposalWorkspace plan.Get started

At a glance

City of Lubbock (Texas) posted this ITB on Nov 15, 2026. Responses are due Dec 10, 2026. Category: Construction - Heavy & Civil. Questions are due no later than five (5) calendar days prior to the bid closing date. Solicitation number ITB 27-20051-AE.

Solicitation details

General information

Solicitation number
ITB 27-20051-AE
Notice type
ITB
Place of performance
Texas
Questions due
no later than five (5) calendar days prior to the bid closing date

Agency and category

Agency
City of Lubbock
Category
006Construction - Heavy & Civil
Source listing
Link with a plan

About this listing

ProposalWorkspace summary

This bid was found on the agency's procurement portal. The portal's own text is not republished here; the summary below was written by ProposalWorkspace's AI from the bid documents. The full posting is on the portal - subscribe to get the link.

Summary

AI-read from the bid documents

Summary fields on this page were extracted by AI from the bid documents. Always verify dates, amounts and requirements against the official solicitation.

What the bid is for

Bidders may submit responses electronically by uploading required documents at the City of Lubbock’s partner website, Bonfire. This Invitation to Bid is for your convenience in submitting a bid for the specified project.

Bids will be opened [...] to furnish all labor and materials and perform all work for the construction of the above referenced.

Scope

The construction covered by the contract documents shall be substantially completed within **125 consecutive calendar days** from the date specified in the Notice to Proceed issued by the City of Lubbock to the successful bidder.

Notice to proceed will be issued 30 days following the award of the contract by the Lubbock City Council.

Unless otherwise specified herein, the City shall award the bid based on the total bid for Bid Items 1-1 through 1-9 plus the sum of any Alternate Bids or Options the City may select.

All equipment and materials incorporated in the project and all construction shall be guaranteed against defective materials and workmanship. [...] the Contractor shall remedy any defects in the work, and pay for any and all damages of any nature whatsoever resulting in such defects, when such defects appear within ONE year from date of final acceptance of the work as a result of defective materials or workmanship, at no cost to the Owner (City of Lubbock).

Additional information

Submission method

Bidders may submit responses electronically by uploading required documents at the City of Lubbock’s partner website, Bonfire. If submitting electronically, do not submit paper documents. If you choose to submit in hard copy, submit one original paper copy of your submittal to the office of the Director of Purchasing and Contract Management. The City will not accept fax bids.

Bids are due at **2:00 PM on December 10, 2026**. Please allow time to upload required documentation. 24hrs in advance is recommended.

Bid security and bonds

Bidders are required, whether or not a payment or performance bond is required, to submit a cashier's or certified check [...] or a proposal bond from a reliable surety company, payable without recourse to the order of the City of Lubbock in an amount not less than **5%** of the total amount of the proposal submitted. Failure of the bidder to include bid security with the bid submittal shall constitute a nonresponsive bid and result in disqualification of the bid submittal.

The successful bidder will be required to furnish a performance bond in the amount of **100%** of the total contract price in the event that said contract price exceeds **$100,000** and a payment bond in the amount of **100%** of the total contract price in the event that said contract price exceeds **$50,000**.

Evaluation

All bids are evaluated for compliance with specifications before the bid price is considered. In case of tie bids, preference will be given to local bidders.

Insurance

The Contractor shall not commence work under this contract until he has obtained all insurance as required in the General Conditions of the contract documents. A certificate of insurance specifying each and all coverages shall be submitted before contract execution.

Prevailing wage

Bidders are required to comply with Texas Government Code, Chapter 2258, Prevailing Wage Rates.

Documents

16 files

Subscribe to get these 16 documents.

  • 01 - ITB 27-20051-AE 2027 Concrete Replacement.pdf
    Download
  • 02a - 2027 Design Standards and Sepecifications.pdf
    Download
  • 02b - Special Conditions Concrete 2027.pdf
    Download
  • 02c - 2027 Map Concrete Replacement Revised 9 30 2026.pdf
    Download
  • 03 - Bid Submittal Form.pdf
    Download
  • 04 - General Conditions of the Agreement.pdf
    Download
  • 05 - Contractors Statement of Qualifications.pdf
    Download
  • 06 - Subcontractors Lists.pdf
    Download
  • 07 - Non Collusion Affidavit.pdf
    Download
  • 08 - Reference Form.pdf
    Download
  • 09 - Safety record questionnaire.pdf
    Download
  • 10 - Insurance Affidavit.pdf
    Download
  • 11 - Conflict of Interest Form.pdf
    Download
  • 12 - Contact Person Form.pdf
    Download
  • 13 - Cons of Local Location.pdf
    Download
  • 14 - Statement of No Bid.pdf
    Download

Similar open bids

In Texas

More from City of Lubbock

Open bids