Engineering Services – Dryer Train Overhaul and Upgrades at Jones Island Water Reclamation Facility

Active J04079D01 RFPArchitecture & EngineeringMilwaukee Metropolitan Sewerage District
The full text, documents and contacts of this bid come with a ProposalWorkspace plan.Get started

At a glance

Milwaukee Metropolitan Sewerage District (Wisconsin) posted this RFP on Nov 12, 2026. Responses are due Dec 10, 2026. Category: Architecture & Engineering. Questions are due One week before Deadline for Receipt of Proposals. Solicitation number J04079D01.

Solicitation details

General information

Solicitation number
J04079D01
Notice type
RFP
Place of performance
Wisconsin
Questions due
One week before Deadline for Receipt of Proposals

Agency and category

Agency
Milwaukee Metropolitan Sewerage District
Category
007Architecture & Engineering
Source listing
Link with a plan

About this listing

ProposalWorkspace summary

This bid was found on the agency's procurement portal. The portal's own text is not republished here; the summary below was written by ProposalWorkspace's AI from the bid documents. The full posting is on the portal - subscribe to get the link.

Summary

AI-read from the bid documents

Summary fields on this page were extracted by AI from the bid documents. Always verify dates, amounts and requirements against the official solicitation.

What the bid is for

The Milwaukee Metropolitan Sewerage District (District) is issuing this Request for Proposals (RFP) to solicit proposals from qualified vendors for Engineering Services for Dryer Train Overhaul and Upgrades at Jones Island Water Reclamation Facility (JIWRF).

The Dewatering and Drying (D&D) Facility is located at the District’s Jones Island Water Reclamation Facility (JIWRF). The D&D Facility (Building 258) produces Milorganite® using Dryers and have been in service since the facility went online in 1994. The equipment is original to the building. Some components have been replaced or overhauled, while others are beyond their original estimated useful life. To meet the goals of the District’s 2022 Biosolids Advanced Facility Plan, the D&D Facility must function reliably for the next 15 to 20 years until the District constructs a new drying facility at South Shore WRF and replaces a portion of the existing D&D Facility at JIWRF.

This engineering services contract encompasses two parts:

1. Product Cooler Replacement
2. Dryer Train Overhaul and Upgrades

The product cooler replacement is a high priority.

Scope

The general scope of services for this contract includes the following major tasks and activities:

A. Project Management

  • Review of existing reference information.
  • Meetings with representatives from the District and Veolia Water Milwaukee (Veolia Water).

B. Preliminary Engineering Services

- Evaluations and recommendations summarized in a preliminary engineering report.

C. Design Services

  • Product cooler basis of design TM.
  • Dryer train evaluation and recommendations summarized in a design report.
  • Construction strategy analyses to minimize disruption to facility operations during construction.
  • Preparation of two sets of bid and construction documents.

D. Bid and Award Services

  • Pre-bid presentations and site tours.
  • Prepare and submit addenda as needed.
  • Respond to bid questions during bidding periods.

E. Engineering Services During Construction

  • Attend construction meetings.
  • Review contractor submittals.
  • Respond to requests for information.
  • Delivery of record drawings.

F. Operation & Maintenance (O&M) Manuals, Training and Start-Up

- Preparation of start-up plans, updates to facility O&M manuals, and staff training.

G. Applications Engineering

  • Control descriptions and PLC programming.
  • Functional acceptance testing.

The detailed Scope of Services is in Attachment A.

Additional information

All proposals must be submitted electronically using the District’s Euna Procurement portal. All proposals must be submitted no later than **12/10/2026 at 10:00 am CT**. Late submissions will not be accepted.

Proposals will only be accepted from firms authorized to do business in the State of Wisconsin.

The selected proposer will provide proof of insurance coverage upon contract execution. The specific insurance requirements are detailed in the draft contract provided in *Attachment E*.

The SBE participation goal for this contract (expressed as a percentage of the total contract dollar amount) is **20%**.

The District’s budget range for the Scope of Services outlined in Attachment A is **$2,200,000 to $2,450,000** (including all contingencies, allowances and estimated costs).

The District’s standard contract is a Fixed Hourly Rate plus Expenses Not to Exceed Contract, except where the contract is for “on-call” services.

IN-PERSON TOUR: A site tour will be conducted to provide vendors with an opportunity to inspect the project location and gather pertinent information. Attendance at the site tour is encouraged to ensure a comprehensive understanding of the contract scope and requirements.

Documents

3 files

Subscribe to get these 3 documents.

Similar open bids

In Wisconsin

More from Milwaukee Metropolitan Sewerage District

Open bids