ProposalWorkspaceFederal OpportunitiesDepartment of Defense

15kV Switchgear & Station Service Replacement at Lake Tenkiller, OK

No due date W912BV26RA032 PresolicitationTotal Small Business Set-Aside (FAR 19.5)Department of the Army
The full text, documents and contacts of this bid open with a free account.Sign up free to read it

At a glance

W076 Endist Tulsa of Department of the Army posted this Presolicitation on Oct 27, 2026. No response date is listed. NAICS 238210 (Electrical Contractors and Other Wiring Installation Contractors), product or service code Y1NZ (Construction of Other Utilities). Set-aside: Total Small Business Set-Aside (FAR 19.5). Place of performance: Oklahoma. Solicitation number W912BV26RA032.

Solicitation details

General information

Solicitation number
W912BV26RA032
Notice type
Presolicitation
Set-aside
Total Small Business Set-Aside (FAR 19.5)
Place of performance
Oklahoma

Classification

NAICS
238210Electrical Contractors and Other Wiring Installation Contractors
Product or service
Y1NZConstruction of Other Utilities

Agency

Department
Department of Defense
Sub-tier
Department of the Army
Office
W076 Endist Tulsa

Description

From SAM.gov

*This Pre-Solicitation Notice is being updated to notify industry that the solicitation number for this requirement has been updated to W912BV27RA003. The Solicitation has been posted on 27 OCT 2026. 

Pre-solicitation Notice

For

15kV Switchgear & Station Service Replacement

at Lake Tenkiller, OK

This is a PRE-SOLICITATION NOTICE for the construction of a 15kV Switchgear & Station Service Replacement at Lake Tenkiller, in Oklahoma. THIS IS NOT A SOLICITATION FOR PROPOSALS AND NO CONTRACT WILL BE AWARDED FROM THIS SYNOPSIS.  No reimbursement will be made for any costs associated with providing information in response to this pre-solicitation notice or any follow up postings.

The U.S. Army Corps of Engineers – Tulsa District has been tasked to solicit for and award a contract to perform the 15kV Switchgear & Station Service Replacement at Lake Tenkiller, Oklahoma. The proposed design-bid-build project will be procured as a Small Business Set-Aside, firm-fixed price contract in accordance with Revolutionary FAR Overhaul (RFO) Part 15, Negotiated Procurement, using the Lowest Price Technically Acceptable approach. Tradeoffs will not be permitted.

Project Description:

The work includes Replace the three existing 15kV switchgear lineups for the generator breakers and station service transformer feeder breakers.

  • Removal of existing 500 kVA, 13.8 kV/480V station service transformer
  • Removal of existing 15 kV switchgear and breakers located beneath control room
  • Removal of 480V station service switchgear in control room
  • Removal of the existing 15kV cables to the switchyard
  • Removal of existing potheads for the 15kV cable transition to switchyard bus
  • Removal of the existing asbestos cable trays containing 15kV cables in cable tunnel
  • Installation of new 15kV cables to the switchyard
  • Installation of new potheads for the 15kV cable transition to switchyard bus
  • Installation of new cable trays containing the new 15kV cables in cable tunnel
  • Installation of front accessible double-ended 480V switchgear beneath control room with feeder

circuit breakers

  • Installation of 15kV switchgear with new vacuum circuit breakers and redundant 500 kVA

13.8kV/480V, high-resistance grounded wye station service transformers

  • Reconfiguration of project diesel generator to wye-grounded with high-resistance grounding

resistor.

  • New control and annunciation wiring for new 480V and 15kV switchgear where existing cables

are not reused.

  • Modifications to protective relay settings and new protection relays for the new station service

feeders.

  • Automatic transfer functionality for the 480V switchgear main & tie breakers, along with local arc

flash mitigation switches.

  • Replacement and relocation of existing Lighting Transformer

The estimated magnitude of construction for this project is between $5,000,000 and $10,000,000.

The North American Industrial Classification System (NAICS) Code for this procurement is 238210, Electrical Contractors and Other Wiring Installation Contractors, which has a small business size standard of $19M.

The Product Service Code is: Y1NZ (Construction of Other Utilities)

Estimated duration of construction of this project is 900 calendar days.

Anticipated solicitation issuance date is on or about 20 July 2026, and the estimated proposal due date will be on or about 19 August 2026.