ProposalWorkspaceState OpportunitiesDistrict of Columbia

Cardozo Education Campus HVAC Upgrades

Active OpenGov-e4aa9e9c RFPConstruction - BuildingDepartment of General Services
The full text, documents and contacts of this bid open with a free account.Sign up free to read it

At a glance

Department of General Services (District of Columbia) posted this RFP on Nov 2, 2026. Responses are due Nov 12, 2026. Category: Construction - Building. Solicitation number OpenGov-e4aa9e9c.

Solicitation details

General information

Solicitation number
OpenGov-e4aa9e9c
Notice type
RFP
Place of performance
District of Columbia

Agency and category

Agency
Department of General Services
Category
005Construction - Building
Source listing
Link after sign-up

About this listing

ProposalWorkspace summary

This bid was found on the agency's procurement portal. The portal's own text is not republished here; the summary below was written by ProposalWorkspace's AI from the bid documents. The full posting is on the portal - sign up free to get the link.

Summary

AI-read from the bid documents

Summary fields on this page were extracted by AI from the bid documents. Always verify dates, amounts and requirements against the official solicitation.

What the bid is for

The District of Columbia (the “District”) Department of General Services (“DGS” or the “Department”), on behalf of the District of Columbia Public Schools (“DCPS”) is seeking a design-builder (the “Design-Builder” or “Contractor”) to perform this scope of work at the Cardozo Education Campus HVAC Upgrades (“the Project”).

This Project addresses system aging, operational deficiencies, and deferred maintenance through a targeted program of capital renewal and system optimization. The work includes replacement and upgrades of select HVAC equipment, repairs to existing systems, enhancements to the building automation system (“BAS”) and controls, comprehensive preventive maintenance measures, and retro-commissioning to restore and verify system performance.

The Project design-to-budget is **$3, 500,000** for construction hard costs.

Scope

Project Goals

  • Complete a comprehensive equipment survey.
  • Restore design functionality to all equipment and controls.
  • Repair or replace defective equipment.
  • Upgrade the building controls systems.
  • Retro-commission (RCx) to the HVAC and BAS to verify conformance to design parameters.

Performance Criteria

The scope of the Project generally includes, but is not limited to, the following. The Contractor shall:

  • Survey each piece of equipment to evaluate condition and estimate life cycle position.
  • Identify assets using refrigerants subject to the American Innovation and Manufacturing (“AIM”) Act phasedown.
  • Identify all upgrades necessary to bring equipment to Day-1 design conditions.
  • Complete upgrades and replacements approved by DGS. This includes AHUs, RTUs, cooling towers, water-source heat pumps, central plant HVAC equipment, etc.
  • Replace the existing Siemens BAS/Desigo CC building management system with a non-proprietary system. Replace controllers and control devices.
  • Upgrade the existing Delta enteliWEB system to the latest version. Update the graphics and build out the central plant. Install power and water submeters and integrate them into the trending platform.
  • Replace the controllers at each AAON AHU, RTU, and ERV with open-source, programmable, BACnet controllers.
  • Install a second plate and frame heat exchanger in the central plant to facilitate future maintenance and resiliency.
  • Complete an ASHRAE Level 3 Energy Audit.
  • RCx to the HVAC and BAS following ASHRAE Standard 202—Commissioning Process for Buildings and Systems. RCx shall be completed by a qualified Commissioning Provider (CxP).
  • Improve safe access to rooftop-mounted equipment by replacing existing vertical ladders with aluminum stairs or 60° ship ladders with platforms conforming to OSHA 1910.25 Stairways.
  • Include permit expediting services as part of the Preconstruction Fee or Design Fee.

The Contractor’s scope of work will be divided into two Phases: (i) the Design and Preconstruction Phase; and (ii) the Construction Phase.

Additional information

**Site visit:** The Contractor shall be required to visit the site, become familiar with local conditions under which the work is to be performed, and correlate personal observations with requirements of the performance criteria and scope of work.

The Contractor shall include with the proposal a recovery plan to address potential non-conforming products or services, such as damaged materials or errors in measurement.

The Design-Build Fee shall be allocated with fifteen percent (15%) of the Design-Build Fee to the Preconstruction Phase (“Preconstruction Fee”), and eighty-five percent (85%) to the Construction Phase.

Allowances

  • Owner Controlled Allowance: **$25,000.00**
  • Building Permit Fee Allowance: **$25,000.00**

Project Delivery Schedule

  • Project Kickoff Meeting: 1 week from NTP
  • Substantial Completion Date: **August 30, 2027**
  • Final Completion Date: **December 29, 2028**
  • Administrative Term Date: **December 30, 2031**

Documents

18 files

Sign up free to get these 18 documents.

  • 2026_Living_Wage_Notice_and_Fact_Sheet.pdf
    Download
  • Bid_Bond_Form.pdf
    Download
  • Department_of_General_Services_Standard_Contract_Provisions_for_Construction_Contracts.pdf
    Download
  • Performance_and_Payment_Bonds.pdf
    Download
  • Bid_Form_-_RFTOP-CS-0179-Cardozo_EC_HVAC_Upgrades.pdf
    Download
  • DGS_Configuration_Management_Policy_Compliance.pdf
    Download
  • First_Source_Employment_Agreement_and_Revised_Employment_Plan.pdf
    Download
  • Campaign_Finance_Reform_Act_Self-Certification_Form.pdf
    Download
  • Title_29_Code_of_Federal_Regulations_(CFR)_Part_5.5_Davis_Bacon_Provision.pdf
    Download
  • Certification_to_Furnish_Performance_and_Payment_Bond.pdf
    Download
  • Davis_Bacon_Wage_Determination_Act.pdf
    Download
  • Equal_Employment_Opportunity_(EEO)_Policy_Commitment.pdf
    Download
  • Tax_Affidavit.pdf
    Download
  • SBE_Subcontracting_Plan.pdf
    Download
  • RFTOP-CS-0179-Cardozo_EC_HVAC_Upgrades.pdf
    Download
  • Scope_of_Work_-_RFTOPCS0179-Cardozo_EC_HVAC_Upgrades.pdf
    Download
  • Bid_Guaranty_Certification.pdf
    Download
  • DGS_Standard_Contract_Provisions_for_Architectural_and_Engineering_Services_Contracts.pdf
    Download

Similar open bids

In District of Columbia

More from Department of General Services

Open bids