Little Village HS Chiller 2 A2 Compressor Replacement Bid - Open to contracted pre-qualified pool for VARIOUS TRADES ONLY

Active 26-1489 ITBFacilities & JanitorialChicago Public Schools
The full text, documents and contacts of this bid come with a ProposalWorkspace plan.Get started

At a glance

Chicago Public Schools (Illinois) posted this ITB on Nov 11, 2026. Responses are due Nov 24, 2026. Category: Facilities & Janitorial. Questions are due Two (2) business days prior to bid closing. Solicitation number 26-1489.

Solicitation details

General information

Solicitation number
26-1489
Notice type
ITB
Place of performance
Illinois
Questions due
Two (2) business days prior to bid closing

Agency and category

Agency
Chicago Public Schools
Category
014Facilities & Janitorial
Source listing
Link with a plan

About this listing

ProposalWorkspace summary

This bid was found on the agency's procurement portal. The portal's own text is not republished here; the summary below was written by ProposalWorkspace's AI from the bid documents. The full posting is on the portal - subscribe to get the link.

Summary

AI-read from the bid documents

Summary fields on this page were extracted by AI from the bid documents. Always verify dates, amounts and requirements against the official solicitation.

What the bid is for

Chicago Public Schools - Department of Procurement invites bids for Little Village HS - Chiller 2 A2 Compressor Replacement, located at Little Village HS - 3120 S. Kostner Ave., Chicago, IL 60623. Type of Project: MEP. Pre-Qualified Contractor Pool: Various Trades.

**Provide Labor and Materials:** Provide Overview of Project - For Chiller 2 Compressor A2.

Scope

Provide Labor and Materials:

Provide Overview of Project - For Chiller 2 Compressor A2:

  • Reclaim 134a
  • Disconnect compressor
  • Reconnect compressor and pressurize with Nitrogen
  • After passing pressure test pull vacuum
  • Charge with 134a
  • Start up compressor

Contractor to secure necessary permits. Contractor to field verify dimensions and specifics of all projects listed above before placing bid. Not responsible for contractor errors as a result of non-field verification.

Materials and installation must comply with CPS Standards and Specifications as listed on

  • SECTION 01 73 29 Cutting and Patching
  • SECTION 01 74 19 Construction Waste Management and Disposal
  • SECTION 02 41 19 Selective Demolition
  • SECTION 23 05 13 Common Motor Requirements for HVAC Equipment
  • SECTION 23 05 93 Testing, Adjusting, and Balancing for HVAC
  • SECTION 23 23 00 Refrigerant Piping
  • SECTION 26 05 05 Selective Demotion for Electrical
  • SECTION 26 05 19 Low-Voltage Electrical Power Conductors and Cables
  • SECTION 26 05 26 Grounding and Bonding for Electrical Systems
  • SECTION 26 05 83 Wiring Connections
  • SECTION 23 64 26 Air-Cooled Rotary-Screw Chillers

Secure job site overnight if work is not completed in one day. If building or CPS properties are damaged during construction, contractor to replace and/or repair as necessary. Provide necessary labor and materials to fix/correct issues preventing any or all of the projects to be marked as completed. All work shall be coordinated with the Board authorized representatives to complete in an agreed upon time frame. Contractor is to remove and dispose of materials torn out and any construction debris. All trash must be removed off-site by contractor. Clean the surrounding area and make sure all is swept of debris.

Additional information

**Bids must be submitted online through EUNA/Bonfire.** Bid Cover Sheet must be completed in its entirety, signed, and dated. All work is to be performed during normal working hours. Warranty information, when applicable, is required with your bid submission.

  • $25,000 or more bid price: Bidder must be signatory to relevant union, per the terms of Bidder's contract and applicable Project Labor Agreement(s).
  • $25,000 or more bid price: Bidder must provide a **Bid Bond equal to 5% of the bid price** from Bidder's surety company.
  • $50,000 or more bid price: Bidder must include in their Bid the premium cost for the Payment and Performance Bond in the full amount of their contract. If Bidder fails to furnish the performance bond within seven (7) days after acceptance of the Bidder's Bid by the Board, the Bid acceptance may be rescinded and the Bidder may be precluded from further Bidding with the Board.
  • $75,000 or more bid price, Bidder must complete relevant MBE/WBE at time of bid, even if Bidder is self-performing. Forms and instructions are available at: https://www.cps.edu/procurement/business-enterprise-development/

All bonds must be issued by a surety acceptable to the Board and Licensed by the State of Illinois.

**Walkthrough is mandatory.** MUST be an approved CPS vendor. All questions/requests must be received two (2) business days prior to bid closing.

Documents

2 files

Subscribe to get these 2 documents.

  • Little Village HS Chiller 2 A2 Compressor Cover Sheet.docx
    Download
  • Little Village HS Chiller 2 A2 Compressor Invitation to Bid.docx
    Download

Similar open bids

In Illinois

More from Chicago Public Schools

Open bids