Johnson County (Kansas) posted this RFQu on Nov 12, 2026. Responses are due Dec 18, 2026. Category: Construction - Heavy & Civil. Questions are due 2026-12-08 14:00. Solicitation number 2026-043.
This bid was found on the agency's procurement portal. The portal's own text is not republished here; the summary below was written by ProposalWorkspace's AI from the bid documents. The full posting is on the portal - subscribe to get the link.
Summary fields on this page were extracted by AI from the bid documents. Always verify dates, amounts and requirements against the official solicitation.
This is a Construction Management at Risk (CMAR) services procurement. Johnson County Wastewater (JCW) is seeking a statement of qualifications (SOQ) from firms to provide CMAR services for the Middle Basin Wastewater Treatment Facility (WWTF) Digester & Solids Improvements (“Project”), Contract No. IMB1-C040. This Request for Qualifications (RFQ) is the first phase of a three-phase procurement process for selection of a Construction Manager. Phase I shall be the solicitation of an SOQ and prequalifying a shortlist of firms to advance to Phase II. Phase II shall be the solicitation of a Request for Proposal (RFP) for a more in-depth response from Phase I shortlisted firms, and Phase III shall include an interview with each firm to present their proposed team members, qualifications, project plan, and answer questions.
JCW is seeking SOQs from qualified CMAR firms (or CMAR teams) to supplement JCW’s Design Engineer with assistance during design phase engineering services and develop the cost model that becomes the basis for the Guaranteed Maximum Price (GMP). The estimated total project cost, including engineering, easements, land acquisitions, and construction is **$150 million**, which includes escalation to midpoint of construction in 2031.
Phase 1 Pre-Construction Phase and Preparation of Guaranteed Maximum Price
The Construction Manager shall consult with the County and the JCW’s Design Engineer throughout the development of pre-design, final design, and a Guaranteed Maximum Price (GMP). The general scope of services anticipated for the Pre-Construction Phase includes:
The full preconstruction scope of services will be included with the RFP.
Phase 2 Construction Phase
The general scope of services anticipated for the Construction Phase includes:
The full phase 2 scope of services will be included with the RFP.
Submission method
The SOQ submission must be submitted electronically at https://jocogov.ionwave.net by a respondent and must: (1) be signed electronically by a duly authorized representative of the respondent’s organization; and (2) contain all information required by the RFQ. You must register as a supplier at https://jocogov.ionwave.net at least two (2) business days prior to the RFQ opening to ensure a successful registration. Late submissions will not be considered regardless of the degree of lateness or the reason related thereto, including causes beyond the control of the respondent.
Evaluation
The CMAR solicitation is a three-stage qualifications-based selection process. Members of the Evaluation Committee will independently review and score each submittal based on the criteria listed herein.
Bonding and insurance
Ability to secure required performance and payment bonds with a qualified surety company up to a project cost of **$150,000,000**, demonstrated through a letter from the Surety stating the bonding capacity of the firm and rating of Surety. Provide evidence that the Respondent is insurable at least to the limits and coverages identified in Section 10.1.
Contract term
The Contract resulting from this solicitation process shall be effective once duly executed and will remain in full force and effect until the Project is completed and final payment has been made by the County to the Contractor.