Storrs Hill Lodge Renovation - Site Work

Active 2026-RFx-065 RFPConstruction - BuildingCity of Lebanon
The full text, documents and contacts of this bid come with a ProposalWorkspace plan.Get started

At a glance

City of Lebanon (New Hampshire) posted this RFP on Nov 19, 2026. Responses are due Dec 17, 2026. Category: Construction - Building. Questions are due 2026-12-04 12:00. Solicitation number 2026-RFx-065.

Solicitation details

General information

Solicitation number
2026-RFx-065
Notice type
RFP
Place of performance
New Hampshire
Questions due
2026-12-04 12:00

Agency and category

Agency
City of Lebanon
Category
005Construction - Building
Source listing
Link with a plan

About this listing

ProposalWorkspace summary

This bid was found on the agency's procurement portal. The portal's own text is not republished here; the summary below was written by ProposalWorkspace's AI from the bid documents. The full posting is on the portal - subscribe to get the link.

Summary

AI-read from the bid documents

Summary fields on this page were extracted by AI from the bid documents. Always verify dates, amounts and requirements against the official solicitation.

What the bid is for

The City of Lebanon, New Hampshire (the CITY) Recreation, Arts, and Parks Department (the DEPARTMENT), invites qualified contractors (the Contractor) to participate in the renovation of the Storrs Hill Ski Lodge building located at 60 Spring Street, Lebanon, NH. This exciting project will provide: additional conditioned interior gathering and instructional space; new toilet rooms; upgrades to the kitchen, ski-patrol, and office spaces; replacement of exterior decks and entries, and; upgrades to the building mechanical and electrical and communications systems. [...]

This specific Request for Proposals (RFP) solicits qualified CONTRACTORs to offer proposals for completing the required sitework for the project.

Scope

The sitework contractor (Contractor) shall be responsible for:

  • Installation and maintenance of all temporary erosion and stormwater control measures.
  • Rough excavation.
  • Installation of drainage piping.
  • Backfill and compaction of all fill materials.
  • Forming, reinforcing, and pouring of all concrete footers, foundation walls, and slabs.
  • Installation of all rigid foundation and slab insulation and vapor barriers.
  • Micro grading.
  • Final grading and restoration of lawn areas.

The scope of work is more fully detailed in the plans, specifications, and scope of work documents.

Specific Tasks

  • General. Supply all materials needed to accomplish the scope of work described below.
  • Rough Excavation. New footers and foundation walls. New interior slab subgrade. French drain. (1) porch pier.
  • Drainage Piping. Footer drain piping, stone bed, and fabric. French drain piping, stone bed, and fabric. Sub-slab drain piping and fabric. Coring of existing catch basin for outlet of french drain.
  • Concrete Work. Form and pour footers and new foundation walls with code required reinforcing. Install and compact sub-slab gravels. Install exterior foundation and slab rigid insulation vapor barriers. Form, pour, and finish new interior slab. Form, pour, and finish new exterior deck slab. Install one (1) additional pre-cast porch pier in coordination with the CITY’s carpentry subcontractor.
  • Micro Grading. Perform micro grading of all areas surrounding the lodge to ensure surface water sheets away from the building and entry ways. Install gravel ramps as required to match entry door thresholds.
  • Final Grading and Restoration of Lawn Areas. Blend disturbed areas into existing undisturbed lawns and driveways. Seed, fertilize, and mulch new lawn areas. The CITY will be responsible for watering.
  • Schedule. The Contractor will work closely with the CITY’s Project Manager (PM) to develop a construction schedule that leads to the efficient prosecution of the overall project, to include providing for other contractors to complete their work in a sequenced, timely and efficient manner.
  • Trades Coordination. The Contractor will communicate and coordinate with all other trades who may need to be performing work either at the same time as the Contractor, or whose work is dependent upon the Contractor finishing or partially finishing the Contractor’s own work.
  • Manufacturer’s Technical Information. The Contractor shall provide to the CITY one (1) hard copy and one (1) .pdf formatted digital copy of all installation and operating and maintenance manuals for equipment and fixtures installed in the project.

Additional information

**RESPONSES MUST BE SUBMITTED ELECTRONICALLY TO:** https://LebanonNH.gov/Bids

The City of Lebanon reserves the right to reject any and all Bids and to waive any irregularity in Bidding. The successful Bidder will be required to furnish the necessary Bonds and Insurance Certificates. The City will award this project based on the City’s discretion and may or may not include any or all bid alternatives. All work included in this bid is dependent upon the bid amounts and available funding. Actual quantities are subject to change and will be based upon actual field measurements taken during construction.

If a CONTRACTOR does not have in house resources to complete all of the required work, the CONTRACTOR may subcontract with another contractor who can provided the required work, but the prime CONTRACTOR must be responsible in every way for the work of the subcontractor. The Contract will be with the prime CONCTRACTOR.

Timeline

  • Question Response Deadline: December 11, 2026, 4:00pm
  • Bid Opening (Non-Mandatory): December 18, 2026, 9:00am, Microsoft Teams meeting
  • Substantial Completion: July 30, 2027
  • Final Completion and Acceptance: August 27, 2027

Documents

4 files

Subscribe to get these 4 documents.

  • BID_Binder_REV_11-18-26.pdf
    Download
  • Storrs_Lodge_Sitework_Scope_of_Work.pdf
    Download
  • Storrs_Hill_Lodge_Renovation_-_Site_Work.pdf
    Download
  • RFB_Agreement_Lebanon.pdf
    Download

Similar open bids

In New Hampshire

More from City of Lebanon

Open bids