Pursuant to Utah Procurement Code 63G-6a and Administrative Rule 33, Heber City (City) finds that using a Construction Manager/General Contractor (CM/GC) for this project is in the best interest of the City because a CM/GC will be accessible early in the cost-effective design of the project. This request for proposals (RFP) seeks qualified contractors, licensed and certified as applicable in the State of Utah, to construct new park improvements associated with the Trailhead Plaza (Main Street Park) project.
The project consists of construction of the Heber City Trailhead Plaza improvements to Main Street Park. The work is anticipated to create a flexible civic gathering place that supports daily park use, civic functions, community events, and year-round recreation.
The CM/GC must be capable of and willing to work closely with the City’s representatives and Terracon Consultants Inc. (Architect), through the design phase, providing cost estimates, schedules, and feedback on design details, phasing, and availability of materials selected.
Improvements may include, but are not limited to, multipurpose event seating, an ice-skating ribbon and support buildings, a pavilion, pedestrian pathways, bicycle connections, play and recreation features, shade and site furnishings, restroom or support facilities, parking and service access, utilities and infrastructure, stormwater improvements, landscaping, and irrigation. Final scope, alternates, and phasing will be confirmed in the contract documents.
The project consists of two (2) phases: Pre-Construction (Design) Phase and Construction Phase.
Pre-Construction (Design) Phase
This phase of work includes, but is not limited to: assistance to and coordinating with the City and the Architect for the design development; recommendations for specific language to incorporate into the construction documents; recommendations on value engineering (e.g. ways to reduce risk and decrease cost); review constructability and completeness of plans; develop conceptual construction schedule and construction cost estimates at major project milestones (30% (SD), 60% (DD), 90%); and other tasks as they arise that are needed for a full and complete design of the project.
CM/GC shall develop a GMP for the project within the City’s budget and schedule. [...] Provide regular construction cost estimates to coincide with the project’s design milestones (30%, 60% and 90%) to verify the proposed design aligns with the City’s allocated construction budget.
Construction Phase
This phase of the work consists of the CM/GC furnishing and installing all work as required in the contract documents. [...] The construction period is anticipated to be completed over two construction season(s) (2 years), subject to the approved phasing and schedule.
The CM/GC shall provide construction expertise and contract management and to be contractually responsible for price, schedule and quality during construction.
Submissions and questions will be accepted electronically through the Utah Public Procurement Place (U3P).
**PROPOSAL DUE DATE:** December 8, 2026, at 5 pm
**RFP Questions Due Date:** December 1, 2026, at 5 pm
The Fixed Limit of Construction Cost or FLCC is **$5 million - $20 million**. Liquidated Damages will be assessed in the amount of **$1,500 to $2,500** per calendar day for each day after expiration of the Contract Time.
All proposals must include proof of a valid Utah General Contractor license at the time of submission. Price (Schedule D) must be submitted as a separate document, labeled 'Price Proposal'.
Offerors must achieve a minimum of 70% of the total technical points to advance to the presentation stage. A presentation may be required at the sole discretion of the City.
The highest scoring proposal will be awarded the solicitation.
The CM/GC must furnish the City with all appropriate Bonds and Insurance as required by the contract documents, including but not limited to appropriate insurance, performance bond(s), payment bond(s), etc. Insurance must be at least equal to contract limits and bonds must be for the full value of construction costs for the scope of work to be completed and must comply with applicable state and/or City standards.