Farallon Well No. 3 - Drilling Services

Active IFB No. 32700084 IFBConstruction - Heavy & CivilCity of Buckeye
The full text, documents and contacts of this bid come with a ProposalWorkspace plan.Get started

At a glance

City of Buckeye (Arizona) posted this IFB on Nov 17, 2026. Responses are due Dec 16, 2026. Category: Construction - Heavy & Civil. Questions are due 2026-12-09 15:00. Solicitation number IFB No. 32700084.

Solicitation details

General information

Solicitation number
IFB No. 32700084
Notice type
IFB
Place of performance
Arizona
Questions due
2026-12-09 15:00

Agency and category

Agency
City of Buckeye
Category
006Construction - Heavy & Civil
Source listing
Link with a plan

About this listing

ProposalWorkspace summary

This bid was found on the agency's procurement portal. The portal's own text is not republished here; the summary below was written by ProposalWorkspace's AI from the bid documents. The full posting is on the portal - subscribe to get the link.

Summary

AI-read from the bid documents

Summary fields on this page were extracted by AI from the bid documents. Always verify dates, amounts and requirements against the official solicitation.

What the bid is for

The City of Buckeye is seeking Bids from qualified contractors for the Farallon Well No. 3 – Drilling Services. The City of Buckeye's Water Resources Department is requesting a quotation to conduct drilling services for Farallon Well No. 3. The awarded Contractor shall furnish all labor, materials, and equipment to perform the work as outlined in Section 100 - Scope of Work, Section 300 – Bid Forms, and Attachment 4 – Technical Specifications.

Scope

Since the pilot borehole was already drilled and tested and the surface casing was previously installed, the drilling contractor will begin by reaming the test borehole to the specified diameter and target depth for completion as a permanent municipal production well. Following completion of reaming, the drilling contractor will retain a qualified geophysical logging subcontractor to perform a caliper log and deviation survey to verify borehole diameter, geometry, and alignment prior to installation of the permanent well casing and screen. Final well acceptance activities will include observation of casing completion and secure capping of the well, with all construction records incorporated into the final project documentation. Following completion of rig development, the drilling contractor will install temporary test pumping equipment to conduct pump and surge development and support subsequent aquifer testing activities to include Step-Rate Discharge Testing and Constant-Rate Aquifer Testing.

The work to be accomplished under the following specifications consists of completion of a production well at the Farallon Well No. 3 (Well 3) site east of S. Oglesby Road and north of Baseline Road in Buckeye, Arizona (Site). [...] The well completion design (18-inch nominal diameter well casing) is presented in Figure 2 for bidding purposes. The scope of work presented herein also includes post well construction aquifer testing.

All contractors are responsible for verifying site conditions and all measurements and quantities in support of their bid.

Additional information

**Bids** will be received electronically via the City's Procurement Portal website no later than **3:00 PM local time on December 16, 2026**. All forms must be submitted as one file in a .PDF format, with all blank spaces filled, the signature in longhand, and alterations or erasures initialed by the Bidder. Name of the file shall read: (Company Name) - IFB No. 32700084

The City reserves the right to reject any or all Bids, and to award the Contract to the lowest responsive and responsible Bidder, whose bid conforms in all material respects to requirements and criteria set forth in the invitation for bids.

**Bid Security** required: a certified or cashiers' check, upon a solvent bank, or a surety bond in an amount equal to ten percent (10%) of the Base Bid made payable to the City of Buckeye.

The Contractor is required to provide and pay for performance and payment bonds. Bonds shall cover the faithful performance (100%) of the Contract, and the payment of all obligations (100%) arising thereunder.

See Article 12 of the Construction Contract between City of Buckeye and Contractor for all insurance requirements.

All Bids shall remain firm for a period of Sixty (60) Calendar Days after the date of the Bid opening. The Work must be completed within one hundred twenty (120) calendar days.

All contractors engaged in City of Buckeye construction shall be duly licensed by the Arizona Registrar of Contractors.

Construction Budget: $2,000,000.00

Documents

3 files

Subscribe to get these 3 documents.

  • Attachment 4 - Technical Specifications.pdf
    Download
  • IFB No. 32700084 - Farallon Well No. 3 Drilling Services.pdf