Irrigation Pump System Assessment, Design, Supply, and Installation

Active 3637-6 RFPConstruction - Heavy & CivilMaricopa County Community College District
The full text, documents and contacts of this bid come with a ProposalWorkspace plan.Get started

At a glance

Maricopa County Community College District (Arizona) posted this RFP on Nov 13, 2026. Responses are due Jan 8, 2027. Category: Construction - Heavy & Civil. Questions are due 2026-12-04 17:00. Solicitation number 3637-6.

Solicitation details

General information

Solicitation number
3637-6
Notice type
RFP
Place of performance
Arizona
Questions due
2026-12-04 17:00

Agency and category

Agency
Maricopa County Community College District
Category
006Construction - Heavy & Civil
Source listing
Link with a plan

About this listing

ProposalWorkspace summary

This bid was found on the agency's procurement portal. The portal's own text is not republished here; the summary below was written by ProposalWorkspace's AI from the bid documents. The full posting is on the portal - subscribe to get the link.

Summary

AI-read from the bid documents

Summary fields on this page were extracted by AI from the bid documents. Always verify dates, amounts and requirements against the official solicitation.

What the bid is for

The Maricopa County Community College District (MCCCD or District) and Phoenix College (PC) intends to engage the services of a contractor to assess, design, furnish, and install an irrigation pump system capable of utilizing available flood irrigation water to supplement or replace potable water currently used within the College's existing irrigation infrastructure.

The primary purpose of this project is to reduce potable water consumption and associated costs by utilizing available flood irrigation water, where feasible, as an alternative water source for landscape irrigation. The proposed system shall provide adequate water pressure and flow to designated irrigation zones while maintaining the reliability, efficiency, and operational integrity of the existing campus irrigation infrastructure.

The initial project contemplated under this Scope of Work is located at Phoenix College (PC).

Scope

The selected contractor shall be responsible for evaluating existing conditions, determining system requirements, recommending appropriately sized equipment, and providing a complete, fully operational pump system.

The selected contractor shall provide all labor, materials, equipment, supervision, technical expertise, coordination and other services necessary to complete the project in accordance with the approved scope.

The contractor shall identify all work necessary to deliver a complete, functional system, including any work associated with the water source connection, pumping equipment, electrical infrastructure, controls, distribution piping, permitting, and required inspections.

Site Assessment and Existing Conditions

The contractor shall:

  • Conduct a comprehensive site assessment of existing irrigation connections, water sources, piping, valves, electrical infrastructure, and associated equipment
  • Verify the availability, capacity, and operating characteristics of the existing water supply
  • Evaluate existing water pressure, flow rates, and irrigation demand
  • Determine whether the flood irrigation water source provides sufficient volume, flow, and operating availability to support the intended irrigation demand
  • Investigate and document any existing water-use rights, agreements, allocations, or authorizations identified for the proposed flood irrigation water source
  • Evaluate whether potable water backup is required to maintain irrigation service during interruptions or insufficient availability of flood irrigation water

Pump System Design and Equipment Selection

The contractor shall:

  • Perform pump sizing calculations based on anticipated irrigation demand, required flow rates, and operating pressure
  • Specify the proposed pump manufacturer, model, horsepower, flow capacity, and operating pressure
  • Evaluate available control options, including manual operation, automatic controls, and variable frequency drives (VFDs)
  • Identify any required storage tanks, holding facilities, filtration equipment, screening systems, or other components necessary to provide a reliable water supply
  • Provide calculations and supporting documentation demonstrating that the proposed pump system can meet the required irrigation demand under anticipated operating conditions

An unprotected direct interconnection between the flood irrigation water system and potable water distribution system shall not be permitted.

Additional information

Submission

MCCCD uses a portal hosted by Euna Procurement (formerly Bonfire) for accepting and evaluating proposals. It shall be the responsibility of the Proposer to confirm that proposals contain all required documents and are submitted electronically through the MCCCD Procurement Portal. Your proposal must be completed and uploaded to our site no later than **3:00 P.M. (local time)**. Submissions after this date and time will automatically be rejected by the system.

No proposal shall exceed forty (40) typewritten pages in length plus any pricing schedule(s), exhibits, resumes, proposed draft revenue sharing agreement, or attachments.

Award

The award shall be made on the proposal(s) that serves the best interest of the District and will not be evaluated solely on a monetary basis. Oral presentations will be evaluated.

Term

It is the intent of the District to award a 1-year contract for a total potential contract term of five (5) years. No billable work is to be done without a signed PO and scope of work.

No proposal may be withdrawn or modified after that deadline and shall be binding upon Proposer for a period of ninety (90) days after due date.

The pre-proposal meeting is NOT a Mandatory Meeting, but Site Tour will follow.