Notice is hereby given that bids for the construction of The Lolo Street Bridge Replacement Project will be received by Missoula County Public Works Department, 6089 Training Drive, Missoula, MT 59808 until 10:00 A.M., local time, on Thursday, November 19th, 2026. [...] The Lolo Street Bridge Replacement Project consists of all work described in the contract documents, which includes but is not necessarily limited to: bridge, sidewalk, road, and water main construction.
The Lolo Street Bridge Replacement Project consists of all work described in the contract documents, which includes but is not necessarily limited to: bridge, sidewalk, road, and water main construction.
Replacement of the Lolo Street Bridge and its associated site work. This consists of all work described in these contract documents, which includes bridge, sidewalk, road, and water main construction.
The sealed bids will then be opened by the County and read aloud at the Missoula County Public Works Office at 6089 Training Drive, Missoula, MT, 59808. No bid may be withdrawn after the scheduled time for the public opening of bids.
The project is primarily funded by a federal PROTECT Grant with some state and local funds and is subject to all applicable federal, state, and local regulations as indicated within the project manual. All work must be substantially complete within **400 calendar days** after the commencement date stated in the notice to proceed. Notice to proceed is flexible with the latest completion date of January 31, 2028.
Plans and specifications may be examined beginning Thursday, October 29th, 2026, on the Missoula County website at https://www.missoulacounty.gov/departments/auditor/bids-proposals/.
The Missoula County Public Works Department reserves the right to waive informalities, to reject any and all bids received, and, if all bids are rejected, to re-advertise under the same or new specifications, or to make such an award as in the judgment of its officials best meets the County's requirements.