California Department of Parks and Recreation (California) posted this IFB on Oct 19, 2026. Responses are due Nov 17, 2026. Category: Construction - Building. Questions are due 2026-11-10 14:00. Solicitation number 0000040702.
Install interim power poles and meter socket/panels for utility company energization due to fire damage at WILL ROGERS STATE HISTORIC PARK in Los Angeles County, California.
**Job Showing is Mandatory** - see Notice to Contractors included in the Project Manual.
Instructions to Download Bid Package: Prospective bidders may examine and obtain the bid forms, specifications, plans and addenda (if any) by downloading this bid package from this website.
Questions and Answers: Any discrepancies, omissions, ambiguities, or conflicts in or among the contract documents or doubts as to meaning shall be brought to the State's attention by emailing your questions to merrilee.byrnes@parks.ca.gov NO LATER THAN 2 p.m., seven (7) calendar days prior to bid opening date. Answers will be provided by Addendum on this website, and it is the responsibility of the bidders to download any addendum as needed.
Participation in Disabled Veteran Business Enterprise Program (DVBE): The minimum DVBE participation percentage goal is 6%. Failure to fulfill the DVBE requirement will render your bid non-responsive. DVBE Incentive: For evaluation purposes only, an incentive will be given to bidders who exceed the 6% DVBE participation requirements. Refer to the DVBE forms beginning with DPR 479IP.
Small Business Preference and Small Business Subcontractor Participation: A five percent (5%) Small Business Preference will be granted to properly certified small businesses (a completed STD 811 Form must be submitted with the bid proposal).
Public Works Contractor Registration Program ¿ SB 854: 1) No contractor or subcontractor may be listed on a bid proposal for a public works project (submitted on or after March 1, 2015) unless registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5 [with limited exceptions from this requirement for bid purposes only under Labor Code section 1771.1(a)]. 2) No contractor or subcontractor may be awarded a contract for public work on a public works project (awarded on or after April 1, 2015) unless registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5. 3) This project is subject to compliance monitoring and enforcement by the Department of Industrial Relations. Refer to http://www.dir.ca.gov/Public-Works/SB854.html for more information.
Summary fields on this page were extracted by AI from the bid documents. Always verify dates, amounts and requirements against the official solicitation.
Furnish all labor, materials, tools and equipment necessary to install interim power poles and meter socket/panels for utility company energization due to fire damage at WILL ROGERS STATE HISTORIC PARK in Los Angeles County, California, complete and in accordance with the plans and specifications therefore and such addenda thereto as may be issued prior to bid opening date.
**License required:** C-10 (Electrical)
**Engineer's Estimate:** $35,000 to $45,000
Furnish all labor, materials, tools and equipment necessary to install interim power poles and meter socket/panels for utility company energization due to fire damage at WILL ROGERS STATE HISTORIC PARK in Los Angeles County, California, complete and in accordance with the plans and specifications therefore and such addenda thereto as may be issued prior to bid opening date.
The bidder agrees to complete all work within NINETY (90) calendar days from the date of written notice to commence work. This time includes ten (10) calendar days allowed for the contractor to begin work.
Bids must be submitted for the entire work as described herein.
**Submission method:** Bids must be submitted electronically with all necessary fully executed bid submission documents as an attachment in Portable Document Format (PDF) to DPR.PWBIDS@parks.ca.gov no later than **2:00 p.m., Tuesday, November 17, 2026**. Submissions with attached PDF documents in excess of 10 Megabytes in size risk being rejected and can be deemed unresponsive. It is recommended that Bidders submit bids at least an hour in advance of the bid submission deadline to allow for confirmation of bid submission.
Bid will be opened publicly over conference-call, individuals interested in calling into the conference must send their request into DPR.PWBIDS@parks.ca.gov to receive a conference participation access code.
**Contract Term:** 455 Calendar Days from Notice to Proceed. **Work Performance Period:** 90 Calendar Days from Formal Start Work Date.
A job showing will be held at 10:00 a.m., November 3, 2026. Attendance at the job showing is **MANDATORY**. No Bid will be considered from a Prime Contractor that did not attend the mandatory job showing.
The minimum DVBE participation percentage goal is **6%**. Failure to fulfill the DVBE requirement will render your bid non-responsive. A five percent (5%) Small Business Preference will be granted to properly certified small businesses.
Bond requirements for contracts exceeding $5,000 are stated in the General Conditions, *DPR 483*, Section 000700.
Sign up free to get these 3 documents.