Gwinnett County (Georgia) posted this ITB on Oct 21, 2026. Responses are due Dec 9, 2026. Category: Construction - Heavy & Civil. Questions are due 2026-11-18 15:00. Solicitation number PE-77023-NONST-2027-000000793.
This bid was found on the agency's procurement portal. The portal's own text is not republished here; the summary below was written by ProposalWorkspace's AI from the bid documents. The full posting is on the portal - sign up free to get the link.
Summary fields on this page were extracted by AI from the bid documents. Always verify dates, amounts and requirements against the official solicitation.
The Gwinnett County Board of Commissioners (Owner) is requesting Bids for the construction of the following Project pursuant to O.C.G.A. §36-91-20: Tribble Mill Dam No. 2 (Chandler Lake) Rehabilitation, F-0234-49.
This Project includes the following Work: Rehabilitation of a low-hazard (Category II) dam in Tribble Mill Park.
Rehabilitation of a low-hazard (Category II) dam in Tribble Mill Park including:
**Sealed Bids** must be delivered to Owner as specified in Section 00 21 13 *Instructions to Bidders* no later than **2:50 P.M. on December 9, 2026**, to be accepted. The bid opening will be virtual ONLY.
The Project is to be substantially complete and ready for operation within 365 days after the date when the Contract Times commence to run as provided in the General Conditions. The Project is to be complete and eligible for final payment 30 days after the date for Substantial Completion.
Drawings and Specifications must be obtained digitally from Hazen and Sawyer via QuestCDN (https://www.questcdn.com/) for a non-refundable fee of **$22** made online to QuestCDN. All Bidders are **required** to purchase a set of Bidding Documents. Only complete sets will be issued.
A **mandatory** pre-bid conference is scheduled, followed by an optional tour of the project Site. Bids are legal and binding upon the bidder when submitted.