IDIQ
Also called: Indefinite delivery, indefinite quantity, IDIQ contract, Multiple-award IDIQ
Updated
What is IDIQ?
An IDIQ (indefinite delivery, indefinite quantity) contract lets an agency buy an unspecified amount of supplies or services, within a stated minimum and maximum, over a fixed period. Work is ordered through task orders or delivery orders, and on a multiple-award IDIQ the holders compete for each order.
How an IDIQ works
IDIQ contracts are covered in FAR 16.504. The contract sets the scope, the period (base plus options), a guaranteed minimum and a ceiling. Winning an IDIQ is a license to compete for or receive orders, not a promise of revenue beyond the minimum.
A single-award IDIQ gives every order to one contractor. A multiple-award IDIQ has several holders, and under FAR 16.505(b) each must get a fair opportunity to be considered for orders above the micro-purchase threshold, with limited exceptions. Agency-wide or government-wide vehicles such as a GWAC are multiple-award IDIQs.
Bidding IDIQs and their orders
There are two competitions: the IDIQ proposal itself, which often weighs corporate experience and past performance heavily, and then each task order, which may have short turnarounds and its own evaluation criteria. Plan for both: an on-ramp win with no capacity to answer orders earns little.
Common mistakes: counting the ceiling as expected revenue, bidding a vehicle your customers do not use, and treating task order requests as routine when they are full competitions.
State and local governments use similar arrangements under other names, such as master agreements, term contracts, on-call contracts or qualified vendor lists, where an award places you in a pool and individual projects follow. The same lesson applies: being on the list is the start, and the revenue depends on how often the agency uses the vehicle and how well you compete for each project. Ask about historical usage during the questions period, and track the orders or projects placed under similar contracts.
IDIQ in ProposalWorkspace
ProposalWorkspace reads the contract type and vehicle from each RFP into the proposal's details, keeps your contract vehicles in the company profile, and records the vehicle and task order on each past performance reference.
IDIQ: questions and answers
Is an IDIQ a guarantee of work?
Only up to the stated minimum. Beyond that, revenue depends on winning or receiving orders during the contract period.
What is the difference between an IDIQ and a task order?
The IDIQ is the umbrella contract that sets scope, period and ceiling. A task order (services) or delivery order (supplies) is the individual purchase placed under it.
Ready when the next RFP drops.